380 kV Pulgar - Vieselbach line; West section (Bad Sulza - Vieselbach)
According to the planning, the dismantling work of the 380 kV existing line will be carried out after and during the construction of the 380 kV new replacement line.
Lot 6 - section from pylon 206 to pylon 248 / Vieselbach substation
Partial dismantling of the existing 380 kV Pulgar-Vieselbach line:
- Line dismantling from existing pylon 201 to pylon 241 (41 pieces)
- Existing pylons to be retained (old pylon no. 241 - new pylon no. 243)
- Complete dismantling (pylon, foundation and stranding)
Project key figures
Project AreaOverhead Power Lines Germany
Project Start
09.2023
Project End
12.2025
Client
50Hertz Transmission
Indicators
- New pylon construction from pylon 206 to pylon 247 (pylon 248 existing pylon formerly pylon no. 241)
- Cable pull from pylon 205 to pylon 248 / UW Vieselbach
Route length of approx. 16.6 km
- Foundation work and mast erection from mast 205 to mast 247 (42 pieces)
- Installation of HighStep system from pylon 206 to pylon 247 (42 pieces)
Contact
Detlev Ewering
Techn. Managing Director