RAIL NODE ROSSLAU – DESSAU, 2nd CONSTRUCTION PHASE

The projects ‘Section 4, Coswig‘ and ‘Section 6, Rosslau Goods Station, Construction Phase 4’ included restructures of rail systems between Coswig and Piesteritz and a restructure of the Rosslau Goods Station (construction phase 4).
The construction work for this general contractor project includes the following services for DB Netz AG, DB Station & Service AG and DB Energie GmbH:
- construction of tracks and track superstructures / laying of underground cables / drainages for tracks and switches
- construction of control systems, signaling systems and safety systems
- construction of 50 Hz electrotechnical systems
- dismantling and construction of 16 2/3 Hz electrotechnical systems
Together with our joint venture partner BUG Verkehrsbau AG we were awarded the tender for this project in April 2015. The framework conditions in this project were so challenging that our project team was faced with almost impossible tasks every day. Our team completed this project with a lot of commitment and dedication in order to meet the schedule.
- STARTMarch 2015
- ENDJune 2016
- CLIENTDB AG
- KEY FIGURES
158 poles
13,880 m catenary
- CONTACT
Hermann Wogowitsch
+43 1 934 66 87 5551