CATENARY SYSTEMS AT/CH/SI

The Zentralbahn

In the initial stage of the construction phase the existing system had to be removed completely. To the extent possible the materials that had been provided by Zentralbahn were pre-assembled prior to the track closure. We then, for the first time, used a helicopter to set and install the mostly pre-assembled poles on the existing foundations and performed all additional assembly works with various rented equipment.

In the section of the newly constructed tracks and the neighbouring area up to the end of the construction site the assembly works for the overhead line system could only be started three days prior to their operation. All adjustment works were completed on time. No reworking measures were required after the track closure.

  1. START
    October 2016
  1. END
    November 2016
  1. CLIENT

    Die Zentralbahn
  1. KEY FIGURES

    Length of line: 5.3 km
    Number of poles: 158
    Length of catenary: 3.9 km
    Catenary type: N-FL

  1. CONTACT

    Werner Schwendimann
    +41 79 344 75 32

 

European Trans Energy GmbH

Emil-Fucik-Gasse 1, A-1100 Vienna, Austria

+43 1 934 66 87 - 5100

+43 1 934 66 87 - 5110

contact@europten.com

EUROPTEN Deutschland GmbH

Allee der Kosmonauten 33G, 12681 Berlin, Germany

contact@europten.com

EUROPTEN Transmission Germany GmbH

Allee der Kosmonauten 33G, 12681 Berlin, Germany

contact@europten.com


Switch company

 
Imprint | Data protection | Switch company