CATENARY SYSTEMS DE

Upgrade of Route (ABS) 48, Geltendorf – Lindau, VE 06 Hergatz – Lindau

Upgrade of Route (ABS) 48, Geltendorf – Lindau, VE 06 Hergatz – Lindau

The upgraded line from Hergatz to Lindau of Route 48 (Geltendorf – Lindau) starts at kilometre 17.96 of line 4560 (Kißlegg) up to Hergatz station and continues up to kilometre 152.0 of line 5362 (Buchloe – Lindau). The sections include Hergatz station and Lindau-Aeschach station as well as the transfer point Weißensberg.

New catenary systems of the types Re 100/100K and Re 200/100K will be installed at these track sections.

  1. START
    April 2019
  1. END
    August 2020
  1. CLIENT

    DB Netz AG
  1. KEY FIGURES

    480 driven pile foundations
    335 drilled foundations
    811 steel masts (thereof 427 Peiner masts)
    1 km Re100 catenary
    56 km Re200 catenary
    6.5 km railway power lines
    33 switches